San Gabriel Solar
255 MW generation in Milam, TX · In queue since January 2025 · Proposed COD July 2028
255 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
The San Gabriel Solar project is a proposed 255 MW solar generation facility in Milam County, Texas. Developed by San Gabriel Solar LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0185, with a queue entry date of January 28, 2025. The proposed commercial operation date is July 1, 2028.
The point of interconnection for the project is the Tap 138 kV 3750 Vosslake - 3749 Buckholts. The project utilizes photovoltaic solar technology. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
San Gabriel Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV 3750 Vosslake - 3749 Buckholts
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.