Ashra Solar SLF
40.25 MW generation in Uvalde, TX · In queue since April 2025 · Proposed COD June 2028
40.25 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-14
The Ashra Solar SLF project is a proposed 40.25 MW solar generation project located in Uvalde County, Texas. The project, developed by Ashra Solar, LLC, consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0188, with a queue entry date of April 25, 2025, and a proposed commercial operation date of June 14, 2028.
The point of interconnection (POI) for the project is the Tap 69kV bus#5823 UVALDE Switch (UVALDESW9) to bus#5820 UVALDE SUB (UVALDESUB9). The project is listed in the ERCOT queue.
Generated from interconnection queue and public data sources
State
TX
County
Uvalde
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ashra Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 69kV bus#5823 UVALDE Switch (UVALDESW9) to bus#5820 UVALDE SUB (UVALDESUB9)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.