Green Ocelot Storage
178.5 MW hybrid in Kenedy, TX · In queue since January 2025 · Proposed COD November 2028
178.5 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-17
The Green Ocelot Storage project is a proposed 178.5 MW hybrid development in Kenedy County, Texas. The project, developed by Ocelot Solar LLC, consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0189, with a queue entry date of January 28, 2025, and a proposed commercial operation date of November 17, 2028.
The point of interconnection (POI) for the project is Tap 345kV 80076 Ajo 80076 - 8601 Cebolla. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Kenedy
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ocelot Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 80076 Ajo 80076 - 8601 Cebolla
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Green Ocelot Storage