Fluvanna Max BESS
50 MW storage in Scurry, TX · In queue since December 2024 · Proposed COD September 2029
50 MW
Capacity
1
Components
Battery
1y 5m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-14
The Fluvanna Max BESS project is a proposed 50 MW battery storage project located in Scurry County, Texas. Developed by Fluvanna Max Solar LLC, the project consists of a 50 MW battery energy storage system (BESS). It is listed in the ERCOT interconnection queue as entry ERCOT-28INR0202, with a queue entry date of December 19, 2024, and a proposed commercial operation date of September 14, 2029.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is the Dermott Substation, with a 345kV gen-tie line approximately 5.5 miles long connecting the Fluvanna Max BESS project to an assigned bay within the Dermott Substation. The project is co-located with project 29INR0077.
Generated from interconnection queue and public data sources
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Fluvanna Max Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
11305-DERMOTT-345 kV A 345kV gen-tie line, approximately 5.5 miles long, will connect the Fluvanna Max BESS (Co-located with 29INR0077) project to the Dermott Substation (Scurry County), terminating at an assigned bay within the Dermott Substation.
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW