Strawberry Dunes BESS SLF
— hybrid in Atascosa, TX · In queue since February 2025 · Proposed COD June 2028
—
Capacity
0
Components
1y 3m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
The Strawberry Dunes BESS SLF project is a proposed battery storage development in Atascosa County, Texas, with a total capacity of 200 MW. The project, developed by Strawberry Dunes LLC, is a hybrid project that includes both battery energy storage and other unspecified technologies.
The project is listed in the ERCOT interconnection queue as entry ERCOT-28INR0209, with a queue entry date of February 14, 2025, and a proposed commercial operation date of June 30, 2028. The point of interconnection is Tap 138kV ROSSVILLESB8 (5718) to OAKSSW8 (5713). The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
TX
County
Atascosa
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Strawberry Dunes LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV ROSSVILLESB8 (5718) to OAKSSW8 (5713)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.