Gypsum Plains Storage
211.14 MW hybrid in Ector, TX · In queue since January 2025 · Proposed COD June 2029
211.14 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-21
The Gypsum Plains Storage project is a proposed 211.14 MW hybrid development in Ector County, Texas. The project, developed by Gypsum Plains Solar, LLC, consists of battery energy storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0217, with a queue entry date of January 31, 2025, and a proposed commercial operation date of June 21, 2029.
The point of interconnection for the project is the Tap 345kV 11010 Wolf - 18544 Reiter.
Generated from interconnection queue and public data sources
State
TX
County
Ector
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gypsum Plains Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kv 11010 Wolf - 18544 Reiter
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WHCCS2_CC2
- POI Substation
- Wolf Hollow Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Gypsum Plains Storage