Allthorn Solar
231.5 MW generation in Duval, TX · In queue since February 2025 · Proposed COD January 2029
231.5 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-15
The Allthorn Solar project is a proposed 231.5 MW solar generation facility in Duval County, Texas. The project, developed by ALLTHORN SOLAR, LLC, is located within the ERCOT region and consists of photovoltaic solar technology.
The project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0229, with a queue entry date of February 14, 2025. The proposed commercial operation date is January 15, 2029. The point of interconnection is Tap 138 kV BRUNI4A (#8297) - CRESTONI4A (#8695).
Generated from interconnection queue and public data sources
State
TX
County
Duval
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ALLTHORN SOLAR, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV BRUNI4A (#8297) - CRESTONI4A (#8695)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.