Dahlia BESS
102.77 MW hybrid in La Salle, TX · In queue since February 2026 · Proposed COD July 2028
102.77 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2028
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-02
Dahlia BESS is a proposed 102.77 MW hybrid battery energy storage project in La Salle County, Texas. Developed by Dahlia Energy Storage LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0241, with a queue entry date of February 26, 2026. The proposed commercial operation date is July 2, 2028.
The project's point of interconnection (POI) is at the Tap 138 kV 5723 Los Angeles - 5705 Fowlerton.
Generated from interconnection queue and public data sources
State
TX
County
La Salle
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dahlia Energy Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV 5723 Los Angeles - 5705 Fowlerton
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Los Angeles Heights Substation