Hittson Creek Solar
404 MW generation in Callahan, TX · In queue since December 2024 · Proposed COD December 2028
404 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-15
Hittson Creek Solar is a proposed 404 MW solar generation project located in Callahan County, Texas. The project, developed by 174 Power Global Properties, is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0245, with a queue entry date of December 19, 2024. The proposed commercial operation date is December 15, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection is planned for tapping the two 345 kV Lines: Sam Line Reactor (Bus# 68005) - Reata (Bus# 68051) and Latimer (Bus# 68008) - Reata (Bus# 68051). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Callahan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
174 Power Global Properties
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tapping the two 345 kV Lines: Sam Line Reactor (Bus# 68005) - Reata (Bus# 68051) and Latimer (Bus# 68008) - Reata (Bus# 68051).
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.