Rio Vista Solar (ERCOT-28INR0260) — Project Summary

Queue ID
ERCOT-28INR0260
Capacity
553.66 MW
Technology
Solar
Status
active
Location
Pecos, TX
Region
ERCOT
Developer
Rio Vista Solar, LLC
IA Status
Facility Study

Rio Vista Solar

ERCOT-28INR0260BetaActiveSolarERCOTLBNL + Live

553.66 MW generation in Pecos, TX · Proposed COD October 2028

553.66 MW

Capacity

1

Components

Solar

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection
Facilities Study50%
Queue Entry

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-16

About

The Rio Vista Solar project is a proposed 553.66 MW solar generation facility in Pecos County, Texas. The project, developed by Rio Vista Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0260. Its proposed commercial operation date is October 16, 2028, and its interconnection status is currently in the Facility Study phase.

The Rio Vista Solar project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Pecos

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Rio Vista Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV #60393 PigCreek4A _x0013_ #60385 Solstice4A

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.