Pasture Rose Wind
198.7 MW generation in Falls, TX · In queue since March 2025 · Proposed COD June 2029
198.7 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-07
The Pasture Rose Wind project is a proposed 198.7 MW wind generation facility in Falls County, Texas. Developed by Pasture Rose, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0262, with a queue entry date of March 24, 2025. The proposed commercial operation date is June 7, 2029.
The Pasture Rose Wind project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Falls
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pasture Rose, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345KV BUS 3721 STRANGER SW - 3711 BALE_S5
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.