Agricola BESS
— hybrid in Austin, TX · In queue since March 2025 · Proposed COD May 2029
—
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-31
The Agricola BESS project is a proposed hybrid energy storage development in Austin County, Texas, within the ERCOT region. Developed by Agricola BESS LLC, the project consists of battery energy storage technology with a queue entry date of March 24, 2025, in the ERCOT interconnection queue (queue ID ERCOT-28INR0265). The proposed commercial operation date is May 31, 2029.
The project is currently listed as active in the interconnection queue. The point of interconnection is Tap 138kV GEBHARDT (#44700) - Wallis (#44740). The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Austin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Agricola BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV GEBHARDT (#44700) - Wallis (#44740)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.