Soluce Bravo Storage
302.62 MW hybrid in Brown, TX · In queue since January 2025 · Proposed COD September 2029
302.62 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-17
The Soluce Bravo Storage project is a proposed 302.62 MW hybrid development in Brown County, Texas. The project, developed by BNPB1, LLC, consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0270, with a queue entry date of January 13, 2025, and a proposed commercial operation date of September 17, 2029.
The project's point of interconnection (POI) is at the tap 345kV 1444 BROWN - 11441 CORN TRAIL SW CKT2.
Generated from interconnection queue and public data sources
State
TX
County
Brown
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BNPB1, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1444 BROWN - 11441 CORN TRAIL SW CKT2
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BBSES_UNIT1
- POI Substation
- Big Brown Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.