Miracle Ranch Solar SLF
221.6 MW generation in Webb, TX · In queue since February 2025 · Proposed COD June 2028
221.6 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
The Miracle Ranch Solar SLF is a proposed 221.6 MW solar generation project located in Webb County, Texas. Developed by Miracle Ranch LLC, the project is interconnected within the ERCOT region and entered the ERCOT interconnection queue as project number ERCOT-28INR0272 on February 25, 2025. The proposed commercial operation date is June 30, 2028.
The project utilizes photovoltaic solar technology. The point of interconnection is the 138kV North Laredo to Barrera line operated by AEP. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Miracle Ranch LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138kV North Laredo (8909_NLARSW4A) to Barrera (8717_BARRERA4A) - AEP
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Miracle Ranch Solar SLF