Miracle Ranch BESS SLF
— hybrid in Webb, TX · In queue since March 2025 · Proposed COD June 2028
—
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
The Miracle Ranch BESS SLF project is a proposed hybrid battery energy storage project located in Webb County, Texas. Developed by Miracle Ranch LLC, the project has a queue entry date of March 19, 2025, in the ERCOT interconnection queue under queue ID ERCOT-28INR0273. The proposed commercial operation date is June 30, 2028.
The project is interconnected to the 138kV North Laredo to Barrera line owned by AEP. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Miracle Ranch LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138kV North Laredo (8909_NLARSW4A) to Barrera (8717_BARRERA4A) - AEP
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.