Live Oak Wind II
302.63 MW generation in Schleicher, TX · In queue since March 2025 · Proposed COD September 2028
302.63 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-29
The Live Oak Wind II project is a proposed wind generation facility with a total capacity of 302.63 MW. It is located in Schleicher County, Texas, and is being developed by ENGIE IR Holdings LLC. The project is listed in the ERCOT interconnection queue as entry ERCOT-28INR0280, with a queue entry date of March 24, 2025, and a proposed commercial operation date of September 29, 2028.
The Live Oak Wind II project is currently listed as active in the ERCOT queue. Recent news coverage indicates public interest in the project, particularly regarding its impact on the electric grid.
Generated from interconnection queue and public data sources
State
TX
County
Schleicher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ENGIE IR Holdings LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#76003 Big Hill 345kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14