Outrider BESS
302 MW hybrid in Dickens, TX · In queue since June 2025 · Proposed COD September 2028
302 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
The Outrider BESS project is a proposed 302 MW hybrid battery energy storage project located in Dickens County, Texas. Developed by Sanders Hollow Energy Center, LLC, the project consists of battery storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0288, with a queue entry date of June 5, 2025.
The proposed commercial operation date for Outrider BESS is September 30, 2028. The point of interconnection (POI) is the Tap 345 kV 59904 Cottonwood (W_CW_345) - 60500 Edith Clarke (EDITHCLA7A) CKT, approximately 11.13 miles from the Cottonwood Substation and 77.6 miles from the Edith Clarke Substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Dickens
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Sanders Hollow Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 59904 Cottonwood (W_CW_345) - 60500 Edith Clarke (EDITHCLA7A) CKT. Approximately distance from the POI to Cottonwood Substation is 11.13 miles and to Edith Clarke Substation 77.6 miles.
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Cottonwood Sub
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.