Wildflower Storage
359.1 MW hybrid in Navarro, TX · In queue since June 2025 · Proposed COD September 2028
359.1 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
Wildflower Storage is a proposed 359.1 MW hybrid energy project located in Navarro County, Texas. The project, developed by Wildflower Storage LLC, consists of battery energy storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0292, with a queue entry date of June 5, 2025, and a proposed commercial operation date of September 30, 2028.
The project intends to interconnect at the Drane Switch 345 kV substation on the Venus Switch (1906) - Navarro (68091) 345 kV line. Wildflower Storage has been mentioned in recent news coverage related to industry and deals.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Wildflower Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Drane Switch 345 kV substation on Venus Switch (1906) - Navarro (68091) 345 kV line
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DSWL_BES1
- POI Substation
- Venus Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.