Dart Energy Storage A1
50 MW hybrid in Taylor, TX · In queue since February 2025 · Proposed COD November 2028
50 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-30
Dart Energy Storage A1 is a proposed 50 MW hybrid energy project in Taylor County, Texas, being developed by Dart Energy Storage LLC. The project consists of battery energy storage and another unspecified technology. It is listed in the ERCOT interconnection queue as entry ERCOT-28INR0293, with a queue entry date of February 25, 2025, and a proposed commercial operation date of November 30, 2028.
The project is currently listed as active in the ERCOT queue. The point of interconnection is at TAP138KV #6290 ABILENE MAPLE STREET - #6275 ABILENE EAST.
Generated from interconnection queue and public data sources
State
TX
County
Taylor
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dart Energy Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP138KV #6290 ABILENE MAPLE STREET - #6275 ABILENE EAST
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Dart Energy Storage A1