Champion Road BESS
205.2 MW hybrid in Angelina, TX · In queue since February 2025 · Proposed COD September 2028
205.2 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
Champion Road BESS is a proposed 205.2 MW hybrid battery energy storage project located in Angelina County, Texas. Developed by Horizon Energy Storage Greenfield Project Holdings LLC, the project entered the ERCOT interconnection queue on February 14, 2025, under queue ID ERCOT-28INR0300. The proposed commercial operation date is September 30, 2028.
The Champion Road BESS project is currently listed as active in the ERCOT queue. Recent news coverage indicates regulatory interest in the project.
Generated from interconnection queue and public data sources
State
TX
County
Angelina
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Horizon Energy Storage Greenfield Project Holdings LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Tap 3328 Lufkin South - 3324 Lufkin Switch Tap East
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.