Carpet Tech Solar One
110.7 MW generation in Kent, TX · In queue since July 2025 · Proposed COD June 2029
110.7 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
The Carpet Tech Solar One project is a proposed 110.7 MW solar generation facility in Kent County, Texas. The project, developed by CT Solar One, is interconnected within the ERCOT region and utilizes photovoltaic solar technology. It entered the ERCOT interconnection queue as entry 28INR0301 on July 7, 2025, with a proposed commercial operation date of June 1, 2029.
The project is currently listed as active in the interconnection queue. Recent news coverage indicates industry interest in the Carpet Tech Solar One development.
Generated from interconnection queue and public data sources
State
TX
County
Kent
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CT Solar One
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#59911 MHOS 345 kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.