Prairie Power Wind (ERCOT-28INR0307) — Project Summary

Queue ID
ERCOT-28INR0307
Capacity
302.9 MW
Technology
Wind
Status
active
Location
Mitchell, TX
Region
ERCOT
Developer
Prairie Power Wind, LLC
IA Status

Prairie Power Wind

ERCOT-28INR0307BetaActiveWindWind TurbineERCOTLive · ERCOT

302.9 MW generation in Mitchell, TX · In queue since June 2025 · Proposed COD April 2029

302.9 MW

Capacity

0

Components

11 months

In Queue

IA Status

COD target: 2029

Status
as of 2 years ago
Latest milestoneribbon-cutting ceremony · 2024-05-16ABC13 Houston · 2024-05-16
Interconnection

Total Duration

3y 10m

Pre-Study0%
Queue EntryJun 5, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-04-17

About

Prairie Power Wind is a proposed 302.9 MW wind generation project located in Mitchell County, Texas. The project, developed by Prairie Power Wind, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0307, with a queue entry date of June 5, 2025. The proposed commercial operation date is April 17, 2029.

The project has been the subject of recent news coverage, with 14 articles related to industry, regulatory, grid, and development aspects of the project.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Mitchell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Prairie Power Wind, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

TAP 345KV BUS #1058 LONGSHORE_5 - BUS #10053 CATTLEMEN_5

Data Source

Live · ERCOT

DeveloperFengateABC13 Houston · 2024-05-16
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.