Velociraptor Solar II
251.73 MW generation in Ector, TX · In queue since May 2025 · Proposed COD November 2028
251.73 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-17
The Velociraptor Solar II project is a proposed 251.73 MW solar photovoltaic generation facility in Ector County, Texas. Developed by Greyhound Solar 3 LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0322, with a queue entry date of May 27, 2025. The proposed commercial operation date is November 17, 2028.
The point of interconnection is the tap south bus Odessa EHV SW (11028) - Wolf Switch (11010) 345KV section at (31.740371, -102.502076). The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Ector
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greyhound Solar 3 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap south bus Odessa EHV SW (11028) - Wolf Switch (11010) 345KV section at (31.740371, -102.502076)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.