Amphion Solar Phase 2
205.9 MW generation in Atascosa, TX · In queue since April 2025 · Proposed COD May 2029
205.9 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-15
The Amphion Solar Phase 2 project is a proposed 205.9 MW solar generation facility in Atascosa County, Texas. Developed by Amphion Solar, LLC, the project is listed in the ERCOT interconnection queue as entry ERCOT-28INR0343, with a queue entry date of April 21, 2025. The proposed commercial operation date is May 15, 2029.
The project intends to interconnect at the TAP 345KV (#5709) Fowlerton - (#5901) SAN MIGUEL LINE Ckt-2. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Atascosa
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Amphion Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345KV (#5709) Fowlerton - (#5901) SAN MIGUEL LINE Ckt-2
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.