Jaguarundi Energy Storage
152.02 MW hybrid in Nolan, TX · In queue since June 2025 · Proposed COD November 2029
152.02 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-10
The Jaguarundi Energy Storage project is a proposed 152.02 MW hybrid development in Nolan County, Texas. Developed by PowerPulse LLC, the project consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0349, with a queue entry date of June 5, 2025, and a proposed commercial operation date of November 10, 2029.
The point of interconnection for the project is Bus # 1339, Eskota 138kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Nolan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
PowerPulse LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Bus # 1339, Eskota 138kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Jaguarundi Energy Storage