River Boat Power Gas Plant
334.36 MW generation in Mitchell, TX · In queue since August 2025 · Proposed COD June 2028
334.36 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2028
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
River Boat Power Gas Plant is a proposed 334.36 MW gas-fired generation project in Mitchell County, Texas. The project, developed by Champion Creek Power, LLC, consists of gas-fired internal combustion technology. It is listed in the ERCOT interconnection queue as entry ERCOT-28INR0351, with a queue entry date of August 18, 2025, and a proposed commercial operation date of June 30, 2028.
The project is currently listed as active in the queue. The point of interconnection is Tap 345kV 10053 Cattlemen 5 - 76030 Gasconades Creek. The River Boat Power Gas Plant development has been the subject of recent news coverage, appearing in 12 news articles related to industry, regulatory, and deals topics.
Generated from interconnection queue and public data sources
State
TX
County
Mitchell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Champion Creek Power, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 10053 Cattlemen 5 - 76030 Gasconades Creek
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26