Finch Storage
201.3 MW hybrid in McLennan, TX · In queue since June 2025 · Proposed COD September 2028
201.3 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
The Finch Storage project is a proposed 201.3 MW hybrid battery energy storage project located in McLennan County, Texas. Developed by Finch Storage, LLC, the project consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0363, with a queue entry date of June 5, 2025, and a proposed commercial operation date of September 30, 2028.
The point of interconnection for the Finch Storage project is the 165 WINDSORSW 138kV substation. The project has appeared in recent news coverage regarding energy storage development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
McLennan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Finch Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
165 WINDSORSW 138kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Finch Storage