Barranca Wind 2
298.6 MW generation in Jim Hogg, TX · In queue since July 2025 · Proposed COD June 2028
298.6 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2028
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
The Barranca Wind 2 project is a proposed 298.6 MW wind generation facility in Jim Hogg County, Texas. Developed by Barranca Wind Energy, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0376, with a queue entry date of July 29, 2025. The proposed commercial operation date is June 1, 2028.
The point of interconnection for the project is planned to tap the 345 kV CENIZO7C - DELSOL7C line. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Jim Hogg
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Barranca Wind Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap the 345 kV CENIZO7C (#80225) - DELSOL7C (#80307) line.
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Barranca Wind 2