Barranca Wind 2 (ERCOT-28INR0376) — Project Summary

Queue ID
ERCOT-28INR0376
Capacity
298.6 MW
Technology
Wind
Status
active
Location
Jim Hogg, TX
Region
ERCOT
Developer
Barranca Wind Energy, LLC
IA Status

Barranca Wind 2

ERCOT-28INR0376BetaActiveWindWind TurbineERCOTLive · ERCOT

298.6 MW generation in Jim Hogg, TX · In queue since July 2025 · Proposed COD June 2028

298.6 MW

Capacity

0

Components

10 months

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

2y 11m

Pre-Study0%
Queue EntryJul 29, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

About

The Barranca Wind 2 project is a proposed 298.6 MW wind generation facility in Jim Hogg County, Texas. Developed by Barranca Wind Energy, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0376, with a queue entry date of July 29, 2025. The proposed commercial operation date is June 1, 2028.

The point of interconnection for the project is planned to tap the 345 kV CENIZO7C - DELSOL7C line. The project has appeared in recent news coverage regarding renewable energy development in Texas.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Jim Hogg

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Barranca Wind Energy, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap the 345 kV CENIZO7C (#80225) - DELSOL7C (#80307) line.

Data Source

Live · ERCOT

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Barranca Wind 2