Galaxy Storage 2
201.87 MW hybrid in Ellis, TX · In queue since June 2025 · Proposed COD October 2029
201.87 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-30
Galaxy Storage 2 is a proposed 201.87 MW hybrid development project located in Ellis County, Texas. The project, developed by Galaxy Solar 2, LLC, consists of battery energy storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0387, with a queue entry date of June 19, 2025, and a proposed commercial operation date of October 30, 2029.
The project's point of interconnection (POI) is the 3/4-Breaker Ring Bus at 345kV Venus Switch (#1907) BKR 4920 - Navarro Switch (LST) (#68091) BKR 3B3134/3B3127.
Generated from interconnection queue and public data sources
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Galaxy Solar 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3/4-Breaker Ring Bus at 345kV Venus Switch (#1907) BKR 4920 - Navarro Switch (LST) (#68091) BKR 3B3134/3B3127
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.