Penelope Solar
97.5 MW generation in Hill, TX · In queue since July 2025 · Proposed COD December 2028
97.5 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
Penelope Solar is a proposed 97.5 MW solar generation project located in Hill County, Texas. The project, being developed by Ash Creek Project LLC, is interconnected within the ERCOT region under queue ID ERCOT-28INR0404. It entered the interconnection queue on July 21, 2025, with a proposed commercial operation date of December 31, 2028. The point of interconnection is a new substation on the 234 Chatt - 3473 Ash Creek 138kV line.
The Penelope Solar project has been mentioned in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
TX
County
Hill
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ash Creek Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
New sub in the 234 Chatt - 3473 Ash Creek 138kV line
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Penelope Solar