Max 4 Wind
352.6 MW generation in Haskell, TX · In queue since July 2025 · Proposed COD August 2029
352.6 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-08-31
The proposed Max 4 Wind project is a 352.6 MW wind generation facility located in Haskell County, Texas. Developed by Lake Creek Wind, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0408, with a queue entry date of July 29, 2025. The proposed commercial operation date is August 31, 2029.
The project's point of interconnection (POI) is the Tap 345 kV Gauss7D (Bus# 60703) to Quasar7A (Bus# 60712) Transmission Line. The Max 4 Wind project has been the subject of recent news coverage, with four articles categorized as industry-related and regulatory.
Generated from interconnection queue and public data sources
State
TX
County
Haskell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lake Creek Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV Gauss7D (Bus# 60703) to Quasar7A (Bus# 60712) Transmission Line
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26