Yellow Leaf II BESS
205.74 MW hybrid in Kaufman, TX · In queue since July 2025 · Proposed COD September 2028
205.74 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-25
The Yellow Leaf II BESS project is a proposed 205.74 MW hybrid battery energy storage project located in Kaufman County, Texas. The developer is Yellow Leaf 2 BESS LLC. It is listed in the ERCOT interconnection queue as entry ERCOT-28INR0412, with a queue entry date of July 22, 2025, and a proposed commercial operation date of September 25, 2028.
The project is listed as active in the interconnection queue. The point of interconnection is Tap 138kV 2727 CRANDALL1_8 - 2724 KAUFMN_8.
Generated from interconnection queue and public data sources
State
TX
County
Kaufman
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Yellow Leaf 2 BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 2727 CRANDALL1_8 - 2724 KAUFMN_8
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.