Tolivar Power Plant Phase 2
224.5 MW generation in Reeves, TX · In queue since July 2025 · Proposed COD July 2027
224.5 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2027
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-30
The Tolivar Power Plant Phase 2 is a proposed 224.5 MW gas-fired generation project located in Reeves County, Texas. Developed by Pecos Power Plant, LLC, the project consists of internal combustion technology and is interconnected within the ERCOT region. It entered the ERCOT interconnection queue as project ERCOT-28INR0413 on July 29, 2025, with a proposed commercial operation date of July 30, 2027.
The point of interconnection for the project is Tap 138 KV 38055 Saltdraw-38043 COWPEN. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pecos Power Plant, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 KV 38055 Saltdraw-38043 COWPEN
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Tolivar Power Plant Phase 2