Alkali Creek Wind
474.4 MW generation in Fisher, TX · In queue since August 2025 · Proposed COD December 2028
474.4 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The Alkali Creek Wind project is a proposed 474.4 MW wind generation facility in Fisher County, Texas. The project, developed by Alkali Creek Wind, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0415, with a queue entry date of August 18, 2025. The proposed commercial operation date is December 1, 2028.
The project's point of interconnection is Tap 345 kV BUS #1048 Tonkawa - BUS #11050 Dusty Road. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Fisher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Alkali Creek Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV BUS #1048 Tonkawa - BUS #11050 Dusty Road
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.