Maratua Solar
100.51 MW generation in Grimes, TX · In queue since October 2025 · Proposed COD December 2029
100.51 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
The Maratua Solar project is a proposed 100.51 MW solar generation project located in Grimes County, Texas. Developed by BDPU Solar Maratua, LLC, the project consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0426, with a queue entry date of October 3, 2025, and a proposed commercial operation date of December 31, 2029. The point of interconnection is planned as a new 138kV connection on the 9 BEDIAS – 4 IOLA line.
Generated from interconnection queue and public data sources
State
TX
County
Grimes
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BDPU Solar Maratua, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
New 138kV connection on 9 BEDIAS – 4 IOLA
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.