Solarville Wind SLF
— generation in Kaufman, TX · In queue since November 2025 · Proposed COD September 2028
—
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2028
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-19
The Solarville Wind SLF project is a proposed wind generation project located in Kaufman County, Texas, within the ERCOT region. Developed by Ville Solar, LLC, the project has a total capacity that is not specified in available data. The project is listed in the ERCOT interconnection queue as entry ERCOT-28INR0431, with a queue entry date of November 18, 2025, and a proposed commercial operation date of September 19, 2028.
The project's interconnection point is identified as Tap 345 kV (#2432)Tri Corner - (#3105) Elkton. The project is currently listed as "active" in the queue. The Solarville Wind SLF project has been the subject of recent news coverage, with two articles categorized as regulatory matters.
Generated from interconnection queue and public data sources
State
TX
County
Kaufman
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ville Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV (#2432)Tri Corner - (#3105) Elkton
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.