Solarville BESS SLF
— hybrid in Kaufman, TX · In queue since November 2025 · Proposed COD September 2028
—
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2028
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-19
Solarville BESS SLF is a proposed hybrid energy project in Kaufman County, Texas, being developed by Ville Solar, LLC. The project, consisting of battery energy storage, has a total capacity that is not specified in available data. It is interconnected within the ERCOT region under queue ID ERCOT-28INR0432, with an interconnection queue entry date of November 18, 2025. The proposed commercial operation date is September 19, 2028.
The point of interconnection (POI) is Tap 345 kV (#2432)Tri Corner - (#3105) Elkton. The project's interconnection agreement (IA) status is not specified in available data, but the project is currently listed as active in the ERCOT interconnection queue. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Kaufman
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ville Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV (#2432)Tri Corner - (#3105) Elkton
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.