Vista Bluff Wind I "Alternate POI"
290.4 MW generation in Upton, TX · In queue since September 2025 · Proposed COD December 2029
290.4 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
The Vista Bluff Wind I "Alternate POI" project is a proposed 290.4 MW wind generation project located in Upton County, Texas. The developer is Vista Bluff Windpower, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0446, with a queue entry date of September 22, 2025, and a proposed commercial operation date of December 31, 2029.
The project's point of interconnection (POI) is the tap 345 kV (76000) North McCamey - (59903) Bearkat, specifically the Benedum 345 kV station, which LCRA will build as part of 24RPG024.
Generated from interconnection queue and public data sources
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Vista Bluff Windpower, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV (76000) North McCamey - (59903) Bearkat (Benedum 345 kV station that LCRA will build part of 24RPG024).
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.