Oakley BESS
200.96 MW hybrid in Denton, TX · In queue since October 2025 · Proposed COD September 2028
200.96 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2028
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-08
The Oakley BESS project is a proposed 200.96 MW hybrid battery energy storage project located in Denton County, Texas. Developed by Oakley BESS LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-28INR0454. The project entered the interconnection queue on October 6, 2025, with a proposed commercial operation date of September 8, 2028.
The Oakley BESS project consists entirely of battery energy storage. It is currently listed as active in the ERCOT interconnection queue. The point of interconnection is Tap 138 kV 612 BLUHORSE– 684 SPRING.
Generated from interconnection queue and public data sources
State
TX
County
Denton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Oakley BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV 612 BLUHORSE– 684 SPRING
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Oakley BESS