Kilby1 Part 2 Tier1 BESS
560 MW hybrid in Reeves, TX · In queue since January 2026 · Proposed COD January 2028
560 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
COD target: 2028
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-21
The Kilby1 Part 2 Tier1 BESS project is a proposed 560 MW hybrid battery energy storage project located in Reeves County, Texas. Developed by Energy Forge One LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0457, with a queue entry date of January 26, 2026. The proposed commercial operation date is January 21, 2028.
The project consists of battery energy storage and another unspecified technology. It is interconnected at Tap 345 11098 SLKSW – 60404 SOLSTICE Ckt 1 Tap 345 11098 SLKSW – 60404 SOLSTICE Ckt 2.
Generated from interconnection queue and public data sources
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Energy Forge One LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 11098 SLKSW – 60404 SOLSTICE Ckt 1 Tap 345 11098 SLKSW – 60404 SOLSTICE Ckt 2
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.