Mutz Solar
72.82 MW generation in Atascosa, TX · In queue since January 2026 · Proposed COD June 2028
72.82 MW
Capacity
0
Components
4 months
In Queue
—
IA Status
COD target: 2028
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
The Mutz Solar project is a proposed 72.82 MW solar generation facility in Atascosa County, Texas. Developed by AETS Development Holdings LLC, the project consists of photovoltaic solar technology. It is listed in the ERCOT interconnection queue as entry ERCOT-28INR0463, with a queue entry date of January 13, 2026, and a proposed commercial operation date of June 30, 2028.
The project's point of interconnection (POI) is at the Tap 69 kV 5693 San Miguel Tap - 5698 North Calliham Sub. As of the latest data, the project's interconnection status is listed as active. The Mutz Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Atascosa
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
AETS Development Holdings LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 69 kV 5693 San Miguel Tap - 5698 North Calliham Sub
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SAN_SANMIGG1
- POI Substation
- San Miguel Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Mutz Solar