Spectra Solar
1,200 MW generation in Scurry, TX · In queue since December 2025 · Proposed COD November 2028
1,200 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
Signed Dec 2025
Queue → IA
<1 month
IA → COD
2y 11m
Total Duration
<1 month
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-11-16
Spectra Solar is a proposed 1200 MW solar generation project located in Scurry County, Texas. Developed by SE DC Devco, the project consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0486, with a queue entry date of December 23, 2025, and a proposed commercial operation date of November 16, 2028.
The project has an Interconnection Agreement (IA) date of December 29, 2025, and its point of interconnection (POI) is the 59912 Galvani 345KV substation. Spectra Solar has been the subject of recent news coverage, with three articles categorized under the industry sector.
Generated from interconnection queue and public data sources
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
SE DC Devco
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59912 Galvani 345KV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.