Queen Mesa Solar II
300 MW generation in Crane, TX · In queue since June 2024 · Proposed COD March 2031
300 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Facility Study
IA Status
COD target: 2031
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-03-21
Queen Mesa Solar II is a proposed 300 MW solar generation project located in Crane County, Texas. Developed by NextEra Energy Interconnection Holdings, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0013, with a queue entry date of June 13, 2024. The proposed commercial operation date is March 21, 2031, and the project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 300 MW of solar photovoltaic generation. It is planned to interconnect at the 76000 North McCamey 345kV point of interconnection. The Queen Mesa Solar II project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Crane
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
NextEra Energy Interconnection Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76000 North McCamey 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- North McCamey Subsation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.