Funston Solar (Alternative POI Lone Star)
351.4 MW generation in Jones, TX · In queue since February 2024 · Proposed COD July 2027
351.4 MW
Capacity
1
Components
Solar
2y 3m
In Queue
IA Executed
IA Status
Signed Oct 2024
Queue → IA
8 months
IA → COD
2y 9m
Total Duration
8 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-07-01
Funston Solar (Alternative POI Lone Star) is a proposed 351.4 MW solar generation project located in Jones County, Texas. The project, developed by Funston Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0015, with a queue entry date of February 27, 2024. The proposed commercial operation date is July 1, 2027, and the project's Interconnection Agreement (IA) was executed on October 23, 2024.
The proposed project is linked to the existing Funston Solar operating plant (EIA plant ID 67359). Its Point of Interconnection (POI) is at the tap 345 kV 68000 West Shackelford _x0013_ 68004 Phantom Hill Circuit 2. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Funston Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV 68000 West Shackelford _x0013_ 68004 Phantom Hill Circuit 2
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.