Commodus Wind
658.8 MW generation in Briscoe, TX · In queue since July 2024 · Proposed COD July 2029
658.8 MW
Capacity
1
Components
Wind
1y 10m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
5 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-30
The proposed Commodus Wind project is a 658.8 MW wind generation facility located in Briscoe County, Texas. Developed by IP Blackwell, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0031, with a queue entry date of July 22, 2024. The proposed commercial operation date is July 30, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Commodus Wind is the tap 345kV 23914 Tule Canyon - 23900 Alibates. The development project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Briscoe
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Blackwell, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 23914 Tule Canyon - 23900 Alibates
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Tule Canyon Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.