Commodus 2 Solar
502.1 MW generation in Swisher, TX · In queue since March 2025 · Proposed COD July 2029
502.1 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-30
The Commodus 2 Solar project is a proposed 502.1 MW solar generation facility in Swisher County, Texas. The project, developed by IP Blackwell II, LLC, is located within the ERCOT region and consists of photovoltaic solar technology. It is listed in the ERCOT interconnection queue as entry ERCOT-29INR0032, with a queue entry date of March 3, 2025, and a proposed commercial operation date of July 30, 2029.
The point of interconnection for the project is planned at the 345 kV double-circuit line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900). The project's interconnection status is currently active within the ERCOT queue.
Generated from interconnection queue and public data sources
State
TX
County
Swisher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Blackwell II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.