Commodus 2 Wind
641.48 MW generation in Swisher, TX · In queue since March 2025 · Proposed COD July 2029
641.48 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-30
The proposed Commodus 2 Wind project is a 641.48 MW wind generation facility in Swisher County, Texas. Developed by IP Blackwell II, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0033, with a queue entry date of March 3, 2025. The proposed commercial operation date is July 30, 2029.
The point of interconnection for Commodus 2 Wind is planned to tap the 345 kV double-circuit line running from the Tule Canyon substation (Bus# 23914) to the Alibates substation (Bus# 23900). The project utilizes wind turbine technology for electricity generation.
Generated from interconnection queue and public data sources
State
TX
County
Swisher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Blackwell II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tapping the 345 kV Double-Circuit Line from Tule Canyon (Bus# 23914) to Alibates (Bus# 23900)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.