Gusty Windpower
208.5 MW generation in Glasscock, TX · In queue since July 2024 · Proposed COD December 2028
208.5 MW
Capacity
1
Components
Wind
1y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
Gusty Windpower is a proposed wind generation project with a total capacity of 208.5 MW. Located in Glasscock County, Texas, the project is being developed by Ballenger Windpower, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0040, with a queue entry date of July 30, 2024, and a proposed commercial operation date of December 31, 2028.
The project's interconnection status is currently in the Facility Study phase. Gusty Windpower has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Glasscock
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ballenger Windpower, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 59903 Bearkat - 1058 Longshore_5
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Bearkat Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Gusty Windpower