Columbine Wind
295 MW generation in Gonzales, TX · In queue since February 2025 · Proposed COD September 2029
295 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-01
The Columbine Wind project is a proposed 295 MW wind generation facility in Gonzales County, Texas. The project, developed by Wilson Wind LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-29INR0063, with a queue entry date of February 25, 2025.
The proposed commercial operation date for the Columbine Wind project is September 1, 2029. The point of interconnection is TAP 345KV BUS #5380 SHAULA- BUS #5133 ELM CREEK.
Generated from interconnection queue and public data sources
State
TX
County
Gonzales
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Wilson Wind LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345KV BUS #5380 SHAULA- BUS #5133 ELM CREEK
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Columbine Wind