Fluvanna Max Solar
150 MW generation in Scurry, TX · In queue since December 2024 · Proposed COD September 2029
150 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-14
Fluvanna Max Solar is a proposed 150 MW solar generation project located in Scurry County, Texas. Developed by Fluvanna Max Solar LLC, the project entered the ERCOT interconnection queue as entry ERCOT-29INR0077 on December 19, 2024. The proposed commercial operation date is September 14, 2029.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Dermott Substation 345 kV, with a planned 5.5-mile 345kV gen-tie line connecting the project to an assigned bay within the substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Fluvanna Max Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
11305 DERMOTT SUBSTATION 345 kV A 345kV gen-tie line, approximately 5.5 miles in length, will connect the Fluvanna Max Solar project to the Dermott Substation (Scurry County), terminating at an assigned bay within the Dermott Substation.
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- JADE_SLR_ALL
- POI Substation
- Dermott Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Fluvanna Max Solar